Nebius plans up to $45 billion 2027 buildout backed by customers
Prepayments and loans against customer contracts are to cover most of the spending, while capacity for Microsoft in New Jersey slips to mid-2027.
Summary

In brief
- Prepayments and contract-backed loans are to cover 75% to 85% of the 2027 spending
- Part of Microsoft’s capacity in Vineland, New Jersey, slips to the second quarter of 2027
- Nebius shares fell 17% on November 12 as 2026 revenue moved to the low end of guidance
Nebius plans $40 billion to $45 billion of capital spending in 2027 and expects prepayments and loans against customer contracts to cover 75% to 85% of it, its letter to shareholders said on November 12.
Nebius, a neocloud that rents out AI computing capacity, funds its growth largely with money customers pay in advance, which ties its financing to finishing data centers on time.
Prepayments on deals signed in the third quarter covered more than 100% of the related capital spending, up from 50% to 60% in the second quarter, and Nebius expects $17 billion to $20 billion of them in 2027, after $10 billion this year. The rest is to come from asset-backed financing, loans secured against long-term contracts. Nebius said its agreements with Microsoft and Meta can be financed this way.
At its Vineland, New Jersey, site, Nebius now expects to deliver more than half of the capacity contracted with Microsoft by the end of the year and the rest in the second quarter of 2027. The contract, signed in September 2025 and worth up to $19.4 billion, set delivery in 2025 and 2026 and lets Microsoft terminate a delayed service after a grace period if no alternative capacity is offered, according to Nebius’s filing on the deal.
DataOne, which operates the site, began retiring its temporary generators late in the third quarter ahead of a move to Bloom Energy fuel cells, a decision that “reset the schedule for the remaining tranches,” Nebius said. New Jersey regulators fined DataOne more than $1 million in September for running 62 natural gas generators there without permits, WHYY reported.
Nebius said Microsoft “has been part of the planning process” but did not say whether it had accepted the new dates. Microsoft is tightening oversight of projects run by Nebius, IREN and Nscale and weighing whether new agreements are worth signing, according to Bloomberg’s November 5 report.
“Where we rely on third parties, there have been delays,” Chief Executive Arkady Volozh wrote. Nebius said the data centers it builds itself, which are to supply most of its new capacity from 2027, are on time or ahead of schedule.
Third-quarter revenue rose 571% to $981 million, including about $325 million of non-recurring revenue from a new partnership model, the company reported. Nebius now expects 2026 revenue at the low end of its $3 billion to $3.4 billion range and capital spending of about $27 billion, above its earlier $20 billion to $25 billion forecast.
Its shares closed down 17% on November 12 and another 10% on November 13, Yahoo Finance data show.
Nebius forecast 2027 revenue of $12 billion to $13 billion and pre-tax breakeven in the fourth quarter of 2027.